Performance Bond Claims should be avoided at all costs. These claims can take a contractor out of business and/or make it very difficult to get bonding in the future. For contractors that do find themselves in a performance bond claim, the information below may be helpful.

 

What Is A Performance Bond?

Performance bonds guarantee that a project will be completed according to the terms and price of the bonded contract. They are a type of contract surety bond and a three party agreement between a Principal, Obligee and Surety. The Principal is the Contractor whose work is being guaranteed. The Obligee is the Owner, Developer or Upstream Contractor who is receiving the benefit of the guarantee. The Surety is the third party bond company who is guaranteeing the Contractor’s performance of the contract. You can find more information on performance bonds here

What is a Performance Bond Claim?

Surety Bond companies underwrite a contractor (Principal) and believe that the contractor can complete the obligation or they would not write performance bonds for the contractor. Similarly, a contractor would not sign a contract and put up a performance bond if they did not believe they could successfully complete that contract. Unfortunately, there are times when a contractor voluntarily admits they can not complete a contract or an Obligee believes the contractor can not complete the project. This creates an opportunity for a performance bond claim. A performance bond claim is a formal claim made to the Surety when it is believed that the Principal contractor will be unable to fulfill the bonded contract. 

 

Review the Contract and Bond Form

The first step for both the contractor and the Obligee before making a performance bond claim should be to review the contract and the performance bond form. The contract and bond form will outline the events that need to occur for a valid performance bond claim. There are many different types of performance bond forms. Some are standardized such as AIA, ConsensusDocs, AGC and others. These bond forms are generally preferred as they provide industry approved conditions for a performance bond claim. However, many Obligees have their own performance bond forms that can have almost any requirements. 

Who Can Make a Claim Against the Performance Bond

The Performance Bond form will also say who can make a claim against the bond. Most performance bonds are written to one obligee. This obligee is usually the project owner, developer, or an upstream contractor. Some bond forms do include a Dual Obligee Rider. This adds another obligee to the performance bond and therefore adds another party that can make a claim on the performance bond. Dual Obligee Riders are usually put in place on private projects to add a lender to the performance bond. 

Contractor Default

Most contracts and performance bond forms require that the Obligee give the contractor notice of “Default” before making a claim on the performance bond. In most circumstances, the contractor has a period of time to “cure” this default. Some performance bond forms provide more time than others to cure the default. Current trends provide cure periods that are so short that it is almost impossible for the Principal to actually cure the default. An example is  “Two Calendar Days”. Some performance bond forms require a meeting between the Obligee, Principal and Surety before a claim can be made against the bond. This gives the Surety and the Principal an opportunity to correct the situation. 

Termination Under the Contract

Most performance bond forms do require a termination for a performance bond claim to proceed. Termination is a formal notice from the Obligee to the Principal that the Principal contractor will not be allowed to finish the incomplete portion of the contract. Until a formal termination occurs, the Principal is still responsible for the contract and nearly all contractors require written notice of a termination.

Elements of a Valid Performance Bond Claim

As discussed, each contract and bond form can be unique, but most require four common elements for a valid performance bond claim:

  1. The Principal has breached the contract. 
  2. The Obligee has declared the Principal to be in default and that default is incurable.
  3. The Obligee has performed their obligations under the contract including payments.
  4. The Obligee has terminated the Principal under the contract. 

 

Performance Bond Claims 4 Requirements - This shows the 4 elements required before a performance bond claim can be filed. The background is a building being constructed with 4 bright color text boxes.

 

Investigating a Performance Bond Claim

Once a surety receives a bond claim from an Obligee on the bond, they must investigate to see if the claim has merit. This includes reviewing the contract, bond forms, laws and statutes and gathering information from the contractor (Principal). This is often a time-consuming process for the Principal and many contractors push back against gathering this information for the surety. However, the General Indemnity Agreement the contractor signed to get bonds, gives the surety access to the contractor’s files and records. Any push back only slows down the process. The contractor should expect to have frequent contact with the surety’s claim staff throughout the process. Surety bond companies are not contractors. Often, they will get third party consultants involved to help in this process.

The surety must investigate the performance bond claim fairly and timely. They must review all available information to determine if a legitimate default and termination has taken place. The surety does not want to proceed with an invalid claim. Doing so, may provide a defense for the Principal and indemnitors so that they would not have to reimburse the Surety Bond Company for costs incurred.

Unfortunately, this is a valid complaint that some Obligees have against performance bonds. The time it takes to investigate a performance bond claim can cause project delays and costs. To combat this, some forward thinking Performance Bond Companies have started offering bond forms that provide some funds to the Principal upfront while the investigation is conducted. 

 

What Could Be Covered Under a Performance Bond Claim?

As we discussed, performance bonds guarantee the performance of a contract. Many different items go into a contractor completing this obligation. Typically, the surety will be responsible for the following during a performance bond claim:

Keep in mind that this is for performance bond claims. Performance bonds are often written along with a payment bond and other claims could have coverage under that bond. 

What Are Defenses to a Performance Bond Claim?

A surety bond company gets to “step into the Principal’s shoes”. That means they do have valid defenses against performance bond claims in these scenarios: 

The Penal Sum Defense

The Penal Sum is the amount of the performance bond. Normally performance bonds are written for 100% of the contract value. The Penal Sum is an absolute defense for surety bond companies on a performance bond. For example, a surety writes a contract for their Principal in the amount of $1 million. Once the project is supposed to be 50% complete, it is discovered that the Principal made a mistake in their estimating. Between remaining costs and delay damages, the Obligee submits a performance bond claim for $2 million. The Penal Sum of the bond is $1 million, and the surety bond company can refuse to pay anything over this amount. 

Depending on the circumstances, the surety could be released of all liability or only the liability that relates to the damage of each defense.

The Surety Bond Company’s Claim Options

Once the surety has investigated the claim, they must decide the best course of action. Some performance bond forms and contracts specify which option the surety must take. Most contracts and bond forms are silent and give the surety one of the following options:

 

Performance Bond Claims - This shows the surety bond company's 4 options during a performance bond claim on 4 construction hardhats. The background is a contractor looking upset.

Tendering a New Contractor

Tendering a new contractor involves a surety company finding a completion contractor to take over the incomplete portion of the work. The surety negotiates a new contract along with the price and terms. Then the surety tenders the completion contractor and new contract to the obligee for approval to complete the project. Usually the new completion contractor provides the obligee new performance and payment bonds for the new contract.

Advantages of Tender:

Disadvantage of Tender:

Tendering a New Contractor is the most common way surety bond companies handle performance bond claims. 

Financing a Principal

Financing the Principal is exactly what it sounds like. The surety company supports the contractor to cure their default on the project and keep them from being terminated. This support can be direct, such as lending the Principal money, or it can be indirect such as guaranteeing bank loans or even in the form of extending more surety credit despite the default. For the surety to finance a Principal, a surety must absolutely believe that the Principal is a very capable company that can turn things around. Normally, this occurs when the surety has exposure on multiple bonded projects and the surety believes the principal can turn things around.

There are advantages and disadvantages to the surety for financing a Principal. These include the following:

Advantages of Financing a Principal:

  1. New Contractor Learning Curve – If a new contractor is selected to complete the project, it will take time to determine where the former Principal was at on the project.  They may even have to deconstruct parts of the project. This creates additional expense to the surety.
  2. New Contractor Markup and Profit – Taking over work for other contractors is risky. Most contractors performing this work do so at a premium to protect themselves. Again, this drives up the cost to the surety.
  3. Subcontractors and Suppliers Cannot Renegotiate – When a new contractor is brought in, subcontractors and suppliers can renegotiate their contracts. They will certainly do so at an increased cost. By financing the Principal, these subcontractors and suppliers remain under their original contracts.
  4. Mobilization – A new contractor will have to mobilize. Depending on the project, these costs can be significant. There could also be some significant de-mobilization costs associated with the Principal and the surety could be liable for these costs. Financing the Principal eliminates these costs. 

Disadvantages of Financing a Principal:

  1. The Principal’s estimates of remaining costs may be inaccurate. When making the decision to finance a contractor, the surety is relying on both the Principal and maybe consultants to make an estimate of remaining costs to complete the project. However, many factors could make these estimates incorrect and the surety could have significantly more costs to complete the project. On the other hand, hiring a new contractor is often at a fixed price and the surety will know exactly what their liability will be. 
  2. The Surety May Have to Cover Unbonded Costs – Often, to keep the Principal going, the surety may have to help with overhead on unbonded projects to keep the contractor in business. This could significantly increase their expense and exposure.
  3. Insolvency – By the time a performance bond claim plays out, the Principal may be insolvent. There may be little motivation to complete the project and/or repay the surety.
  4. Financing Does Not Decrease the Penal Sum on the performance bond. Any money that is lent to the Principal does not decrease the surety’s exposure on the performance bond.

Contractors often incorrectly believe that the surety will finance them. They believe the surety has an interest in providing cash to keep their operations running and completing their work. Surety Bond Companies almost never finance contractors. Doing so opens them up to additional liability and unknown risks. When surety bond companies do provide financing, their interests are in winding down their liability and not in keeping the contractor in business.

 For this reason, contractors would be wise to seek out all other lending solutions before asking the surety to finance them. With SBA backed loans, peer to peer lending, receivable financing and equipment loans, there are many places to look for lending before even considering these options. Although these may have high rates or tough terms, they provide contractors a chance to  continue operations, keep their business running, and maintain control. Financing from surety bond companies is rare and when it happens, the surety usually takes over and puts the contractor out business. 

Takeover

Another option available to the surety is takeover. In a performance bond takeover, the surety “steps into the shoes” of the Principal. By doing so, the surety gives up their right as “surety” and in essence, becomes the contractor. The surety selects a completion contractor and subcontracts the work to them. The surety collects progress payments from the Obligee and pays the completion contractor. This allows the surety to monitor the cash on the project and add to it from their own funds as necessary. The General Indemnity Agreement signed with the Principal normally gives the surety the right to use the Principal’s equipment, inventory and other assets to complete the project. 

Advantages of Takeover:

Disadvantages of Takeover:

Obligee Completion (Do Nothing Approach)

Obligee Completion is often referred to as “The Do-Nothing Approach”. The surety chooses to let the Obligee complete the project. There are valid reasons why a surety may do this. They may feel that the Principal has credible defense to the default such as nonpayment by the Obligee. They could also choose this option if the uncompleted portion of work and damages were close to or exceeding the penal sum of the bond. 

Advantages of Obligee Completion:

Disadvantages of Obligee Completion:

Subrogation Rights

Contractors involved in a performance bond claim should be aware of the surety’s subrogation rights. When a surety gets involved to resolve a performance bond claim, they also get the right of subrogation against the Principal. That means they get to take over the contractual benefits of the Obligee, suppliers and other parties. Normally surety bond companies use this right to get access to contract proceeds. This often plays out against lenders when a contractor gets into financial trouble. Lenders and sureties routinely fight over access to a contractor’s assets such as receivables. However, case law has routinely sided with surety bond companies in these situations. This holds true against other parties as well such as bankruptcy trustees.

The General Indemnity Agreement

Performance Bonds are written on the Principal of Indemnity. That means that if a contractor has a performance bond claim, the surety will seek reimbursement for all costs associated with investigating the claim and paying or completing the project. These obligations are spelled out in the General Indemnity Agreement (GIA) that contractors sign before they can get performance bonds.

It is very important to review this document when you are involved in a performance bond claim. The GIA outlines your responsibilities to the bond company. There are usually requirements to cooperate and provide timely information. The GIA will also spell out who is an indemnitor on the performance bond. The construction company will always be an indemnitor. There could also be related companies, unrelated companies, owners and their spouses or even third-party indemnitors. Generally, these indemnitors are joint and several which means the surety can seek reimbursement from any or all of them. Additionally, the GIA usually has a collateral provision that requires indemnitors to post collateral in favor of the surety if a claim arises.

Getting the advice of a good attorney is a good idea when you are involved in a performance bond claim. Be careful though. Very few have a specialty in performance bond claims, and you want to be working with somebody experienced in this field.

Avoiding Performance Bond Claims

Performance bond claims can take contractors out of business and should be avoided. Below are the two causes of performance bond claims that I have seen frequently throughout my career:

Poor Internal Controls

Every year when surety bond companies investigate what causes most of their performance bond claims, poor internal controls are listed at the top. Many contractors think their systems are sufficient and most are wrong. Construction is a very risky, cash intensive business. Contractors should have systems in place that allows them to see accurate reports on their cash, financial position, job costs, ect. at all times. At the very least this should be reviewed monthly. Project losses, profit fades and billing issues should be addressed immediately. Contractors without these controls often discover problems only after it is too late. 

A second part of internal controls is checks and balances in your estimating department. Make sure projects over a certain dollar amount are checked and rechecked by more than one person. It only takes one bad estimate to put you into a performance bond claim and possibly put the company out of business.

Change Orders

There is never a good reason to perform work without a signed change order. Contractors are always confident that they will get this signed. It is much more difficult to get these change orders signed after the work has been done and costs have been incurred. Unapproved change orders are a significant reason for performance bond claims. 

Subcontractor Default

Subcontractors are the single biggest risk many contractors have on a project. However, many contractors do not want to protect themselves by getting subcontract bonds or other means that will protect them. They feel the extra cost will make them uncompetitive. The fact is that subcontractor problems create huge costs and lost profits. A bad subcontractor may not only create a performance bond claim, it can often take a good contractor out of business.

By having better practices for just these items, contractors can significantly reduce their chances of ever getting into a performance bond claim.

Performance Bond Claims are rare but they do happen. In many cases, the results can be devastating. Understanding how they work can help contractors avoid them. Contractor can also learn about Bid Bond Claims here. Contact Axcess Surety anytime. We are happy to answer any questions and help contractors avoid performance bond claims.

Vice President at Axcess Surety
Vice President of Axcess Surety. Surety Bond and financial expert dedicated to helping contractors, businesses and individuals understand and obtain surety bond credit.
Josh Carson, AFSB
Latest posts by Josh Carson, AFSB (see all)
LinkedInPinPrint
Contact Us

Axcess Surety is the premier provider of surety bonds nationally. We work individuals and businesses across the country to provide the best surety bond programs at the best price.

Headquarters:
5440 W 110th St Suite 300-2
Overland Park, KS 66211
12288 S. Mullen Rd.
Olathe, KS 66062
Copyright © 2024 Axcess-Surety.com ・All Rights Reserved Worldwide
magnifiercrossmenu
Verified by MonsterInsights